During the recent April 30 – May 1 holiday period, Vietnam Global Transport Corporation (VGT) successfully completed the dismantling, transportation, and reinstallation of a 220kV transformer body and its accessories from Phu My 3 BOT Power Plant to Phu My I Power Plant.
Following transportation, the 220kV transformer body and accessories were reinstalled onto the operational foundation at Phu My I Power Plant in accordance with technical requirements.
The entire scope of work was executed within a short timeframe to minimize potential losses for the client caused by the shutdown of a generating unit due to the failure of the main transformer.